Construction costs in Crete in 2026: what a villa, hotel or building really costs
Indicative cost-per-square-metre ranges for residential, hospitality and commercial construction in Crete — and the factors that move the number.
“How much per square metre?” is the first question every owner asks — and the honest answer is a range. Material prices, labour availability, site conditions and the specification you choose all move the number. Below are the indicative ranges we use for early planning in Crete in 2026.
- Standard residence €1,400–1,800
- Apartment building €1,300–1,700
- Premium villa €2,000–2,800
- Luxury villa €2,800–4,200
- Boutique hotel €2,200–3,200
- Commercial shell & core €1,100–1,600
Indicative figures for planning purposes only. Every project is priced individually.
What drives the cost
- Site and foundations: sloping plots, rock and retaining walls add cost quickly.
- Specification: natural stone, large-format glazing and bespoke joinery can double the finishes budget.
- Building services: heat pumps, underfloor heating, solar and smart-home systems.
- External works: pools, landscaping, driveways and boundary walls are often underestimated.
- Access and logistics: remote or narrow-road sites raise transport and crane costs.
Where the money goes
For a typical premium villa, structure and envelope account for roughly two-fifths of the budget, building services around a fifth, and finishes, pool and external works most of the rest.
- Structure & earthworks24%
- Envelope & roofing14%
- MEP services20%
- Finishes & joinery26%
- Pool & external works11%
- Fees & permits5%
Indicative figures for planning purposes only. Every project is priced individually.
What is not in the price per m²
Land, VAT, design fees, permit fees, utility connections, furniture and contingency sit outside most per-square-metre figures. We recommend a contingency of 7–10% for new builds and 12–15% for renovations of older stone buildings.
How to protect your budget
Price the design while it is being developed, not after. At Modera our cost-control team issues an updated cost plan at each design stage, so decisions are made with the numbers on the table — and the final contract reflects a fully defined scope rather than a set of provisional sums.
Budgets rarely fail on site. They fail in the design stage, when nobody was pricing the decisions.
Frequently asked questions
Is it cheaper to renovate a stone house than to build new?
Not always. Structural strengthening, damp remediation and working around existing walls can make restoration as expensive per square metre as a new build, though the character is often worth it.
Do prices include VAT?
No. The ranges shown exclude VAT and land. VAT treatment of new buildings in Greece has changed several times, so confirm the current rules for your transaction.